Project List
Accept Sales Agreement 11/22/2005
Contact Customer for Design Center Appt. (est.) 12/09/2005
Site Meeting 11/23/2005
Deadline for Structural Changes 12/06/2005
Design Center Appt. (est.) 12/16/2005
Check Print Ready for Approval 12/29/2005
Berks Homes Receipt of Buyer-Approved Check Print 01/13/2006
Stake Lot 01/20/2006
Building Permits Received 02/02/2006
Berks Homes to Call for Pre-construction Meeting 02/14/2006
Prints Approved/Released to Field 02/10/2006
Excavate Foundation 02/14/2006
Pour Footers 02/16/2006
Set Foundation Walls 02/21/2006
Remove Foundation Forms 02/23/2006
Foundation Backfill 03/02/2006
First Floor Framing 03/09/2006
Roof Trusses 03/14/2006
Plumbing Rough-in 03/17/2006
HVAC Rough-in 03/17/2006
Berks Homes to Call for Pre-drywall Meeting 03/17/2006
Electrical Rough-in 03/22/2006
Pour Basement/Garage Concrete Floors 03/24/2006
Vinyl Siding 03/28/2006
Insulation 03/29/2006
Drywall 04/06/2006
Trim 04/24/2006
Interior Paint 04/28/2006
Vinyl Floors 05/01/2006
Hardwood Floors (if applicable) 05/02/2006
Cabinets 05/03/2006
Berks Homes to Call for Color Confirmation 05/04/2006
Ceramic Tile Install (if applicable) 05/09/2006
Plumbing Finish 05/11/2006
Electrical Finish 05/12/2006
Berks Homes to Call for Orientation 06/06/2006
Carpet 05/17/2006
Final Cleaning 05/25/2006
Orientation 06/06/2006
Closing 06/07/2006
Settlement06/22/2006